← Back to Blog
Structural steel erection is among the most hazardous activities on any construction project. Ironworkers operate at significant heights, handle heavy components suspended from cranes, and work on incomplete structures that lack the stability of a finished building. The combination of elevation, moving loads, and partially connected steel creates a uniquely dangerous work environment.
In Ontario, structural steel erection is governed primarily by Ontario Regulation 213/91 (Construction Projects), with Part IV addressing specific requirements for structural steel and precast concrete erection. This article covers the key safety requirements and best practices for keeping ironworkers safe on Ontario job sites.
Connection Point Fall Hazards
The most critical moments in steel erection occur at connection points — where an ironworker must position a beam or column, align bolt holes, and make the initial connection. During this process, the worker is typically at height, standing on a beam or in a man basket, reaching to guide steel into place while maintaining balance.
- 100 percent tie-off — ironworkers must maintain continuous fall protection. This means using a dual-lanyard system that allows the worker to stay connected to an anchor point at all times, even while transitioning between locations. At no point should a worker be unconnected while at height.
- Anchor point planning — before steel erection begins, the erection plan must identify anchor points for fall protection at every stage. This includes temporary anchor points on columns, beams, and purpose-built anchor devices. Anchor points must be capable of supporting a load of at least 22.2 kN (5,000 lbs) per worker attached.
- Beam walking — walking along the top flange of an unsecured beam without fall protection is not permitted in Ontario. Workers must use travel restraint or fall arrest any time they are on structural steel at height, regardless of the beam width.
Column Stability and Guying
A steel column standing on its base plate with only anchor bolts tightened is not a stable structure. Until a column has at least two beams connected at different levels and those connections are fully bolted, the column is vulnerable to overturning from wind loads, crane impact, or the weight of steel being placed.
- Temporary guying and bracing — columns must be guyed or braced immediately after being set to prevent overturning. Guy wires should be attached at or near the top of the column and anchored to dead-man anchors or other stable points at ground level.
- Plumbing and securing — columns must be plumbed (verified vertical) and the base connections secured before additional steel is placed on them. Loading an out-of-plumb column creates eccentric forces that can cause collapse.
- Erection sequence — the structural engineer's erection sequence must be followed precisely. The sequence is designed to ensure that each piece of steel is supported by previously erected and secured members. Deviating from the sequence can create instability.
Perimeter Cables and Safety Nets
Perimeter protection is required at every open edge on a steel structure where workers could fall. Ontario Regulation 213/91 requires guardrails at any open edge where a worker could fall more than 2.4 metres, but during active steel erection, perimeter cables are often used as an alternative when conventional guardrails are impractical.
- Perimeter wire rope — a wire rope system installed around the perimeter of each floor level as steel erection progresses. The top cable must be between 0.9 and 1.07 metres above the working surface, with a mid-cable at approximately half that height. Cables must be tensioned to minimize deflection.
- Safety nets — where perimeter cables are not feasible, safety nets may be installed below the work area to arrest falls. Nets must be installed as close as practicable to the work level (no more than 6 metres below) and must extend at least 2.4 metres beyond the edge of the working area.
- Installation timing — perimeter protection must be installed as steel erection progresses, not after. The protection should follow the leading edge of work, with cables or nets going up on each bay as it is completed.
Controlled Decking Zone Procedures
A controlled decking zone (CDZ) is a defined area where metal deck is being installed on structural steel. Within a CDZ, conventional fall protection may not be feasible because the deck itself is not yet secured and cannot support guardrail posts or provide reliable anchor points. CDZ procedures allow decking to proceed under strictly controlled conditions.
- Zone boundaries — a CDZ is limited to the area around the leading edge where deck is being placed. The zone must be clearly defined and marked, typically extending no more than 27 metres (90 feet) from the leading edge.
- Authorized personnel only — only workers actively engaged in decking operations are permitted within the CDZ. All other workers must stay outside the zone boundaries.
- Deck securement — each sheet of metal deck must be secured (welded or mechanically fastened) before the next sheet is placed. Unsecured deck sheets can shift, slide, or blow off in wind, creating both fall and struck-by hazards.
- Wind restrictions — decking operations must be suspended when wind speeds exceed the limits specified in the erection plan. Metal deck acts as a sail in high winds and can become uncontrollable.
Bolt-Up Fall Protection
After initial connections are made with drift pins or a few temporary bolts, the bolt-up crew follows behind to install and tighten the full complement of bolts at each connection. Bolt-up work requires sustained time at height, often in awkward positions, making fall protection critical.
- Dual-lanyard systems — bolt-up workers must use dual-lanyard fall arrest systems to maintain 100 percent tie-off while moving between connections. A single lanyard creates gaps in protection during transitions.
- Retractable lifelines — self-retracting devices (SRDs) are preferred for bolt-up work because they allow freedom of movement while limiting free-fall distance. SRDs should be anchored above the worker's D-ring whenever possible to minimize fall distance.
- Horizontal lifelines — for long runs of beam connections, horizontal lifeline systems allow workers to travel the length of a beam while remaining connected. These systems must be engineered and installed according to the manufacturer's specifications, with attention to maximum span, number of workers, and anchor point capacity.
Crane Coordination During Steel Setting
Every piece of structural steel arrives at its final position by crane. The interface between crane operations and ironworkers is one of the highest-risk activities on any construction project.
- Signal person requirements — a designated signal person must direct crane movements during steel erection. The signal person must have an unobstructed view of both the load and the ironworkers receiving it, and must use standardized hand signals or radio communication.
- Tag lines — every suspended load must have tag lines attached to control rotation and swing. Ironworkers must never use their hands or bodies to guide a free-swinging steel member into position — the momentum of a multi-tonne beam can be lethal.
- Do not unhook until stable — the crane must maintain load control on each steel member until it is securely connected with a minimum of two bolts at each connection point. Premature release of the load can cause the member to fall or shift, potentially causing a collapse.
- Exclusion zones — establish and enforce exclusion zones below active steel erection areas. No workers should be permitted below suspended loads or in areas where steel is being placed. Barricade these zones with caution tape, fencing, or flagging.
- Wind and weather monitoring — crane operations and steel erection must be suspended when wind speeds or weather conditions exceed safe limits. Large steel members catch wind like sails, and crane capacity is reduced in high winds. The crane operator has the authority — and the obligation — to refuse to lift if conditions are unsafe.
O. Reg. 213/91 Part IV — Key Requirements
Ontario Regulation 213/91 Part IV contains specific provisions for structural steel and precast concrete erection. Key requirements include:
- Erection drawings and procedures — a professional engineer must prepare erection drawings and procedures before work begins. These documents specify the erection sequence, temporary bracing requirements, and connection details.
- Competent supervision — steel erection must be supervised by a competent person who understands the erection plan, the structural requirements, and the safety procedures. The supervisor must be on-site whenever erection is in progress.
- Fall protection at 2.4 metres — any worker who may fall more than 2.4 metres must be protected by a guardrail system, travel restraint system, fall restricting system, fall arrest system, or safety net.
- Daily inspections — all structural steel, connections, and temporary bracing must be inspected daily before work begins and after any event that could affect structural integrity (such as high winds or seismic activity).
- Worker training — all workers involved in steel erection must have completed Working at Heights training approved by the Chief Prevention Officer. Additionally, workers should be trained on the specific hazards and procedures of the project they are working on.
Final Thoughts
Structural steel erection demands respect — for the forces involved, for the heights, and for the regulations that exist to protect workers. Every ironworker, supervisor, and project manager involved in steel erection should know these requirements inside and out. The erection plan is not just paperwork — it is the blueprint for keeping everyone alive.
If your ironworkers need Working at Heights certification or renewal, get it done before they step onto the steel. It is one of the most important safety investments you can make on any structural project.
Get Proper Training
Book MLITSD-approved Working at Heights training in Toronto & GTA. Same-day certificates. $150+tax.
View Courses →